Client
Wates
Date of completion
May 2015
Value
£7.8 M
Full Case Study Download
Scope of works
-
Demolition
-
Installation of major temporary works to Grade II listed buildings
-
Bulk excavation (30,000m³)
-
Reinforced concrete frame
-
Top down construction
-
Drainage and pumping chambers
-
Design, installation and removal of the temporary gantry
Project key points
-
Major temporary works including design, installation and removal of props up to 35m in length, 1.3 diameter and weighing up to 20 tonnes
-
Top down construction including the heavily restricted excavation and subsequent disposal of over 30,000m³ of excavated arisings through preformed 'mole holes' below the newly cast suspended slab
-
Carefully planned and systematic triple handling of excavated arisings due to the restrictions imposed by the temporary propping, varying stepped levels/undulations in formation
-
Safe removal of substantially large existing foundations to Grade II listed buildings following installation of temporary piles, needles and props
-
Achieved no more than 10mm cumulative movement across the entire installation, pre-loading and removal of the entire temporary works scheme
Contact Toureen Group
If you are looking for a contractor to undertake major projects, reinforced concrete frames and groundworks, please get in touch with us using the details on our contact page.