Client
Bam Construction Limited
Date of completion
March 2017
Value
£5.4m
Scope of works
-
Sheet piling
-
RC basement and two-storey slip-formed RC cores
Project key points
-
Installation of sheet piles around the perimeter of building
-
Construction of capping beam and installation of propping steel
-
Basement excavation over 7m deep
-
Construction of basement raft slab 1.5m deep and RC liner-wall to front of sheet pile using water proof concrete
-
Installation of below ground drainage system
-
Construction of RC columns, mezzanine floor and ground floor
-
Slip-form two concrete cores 12 floors in height from basement level
-
Concrete to floor slab from 1st to 10th floor on composite floor decking