Project Profile: Chepstow Villas, London

Client
Private Client
Date of completion
September 2011
Value
£1.7m
Chepstow 1
Chepstow 2

Scope of works

 

  • Construction of a double level basement, including a swimming pool, by top down techniques 

  • Enabling works

  • Bulk excavation

  • Piling

Chepstow 3

Project key points

 

  • Structural refurbishment of the existing property - including temporary façade retention, new supporting steel frame and concrete floors

  • 300 contiguous pile wall to the basement perimeter, sacrificial supporting piles (used for top down construction) and permanent tension and bearing piles

  • Sacrificial supporting stools to the existing property that temporarily support the structure and allow the lower ground floor slab to be cast under all existing load bearing walls 

  • Mole holes left in the slab for excavation of basement

  • Bulk excavation of basement top down using the mole holes while the lower ground floor slab and existing structure are supported on the sacrificial piles

  • New reinforced concrete basement sub-structure, including basement slab, lining walls, basement perimeter and new supporting columns

  • New super-structure works, including façade retention, new steel frame and concrete floors on composite metal floor decking, all constructed by taking off the existing roof