Client
Renewable Energy Producer
Date of completion
May 2015
Value
£4.2m
Scope of works
-
Appointed directly by the client, Toureen performed the role of main contractor and oversaw the site being developed from a 9 acre (37,000m²) parcel of green field land to a fully functioning anaerobic digestion facility
-
Groundworks
-
Cut and fill
-
Substructure foundation works
Project key points
-
Substructure foundation works including circular reinforced concrete bases up to 40m² dig, reinforced concrete walls to bunded storage area, flood defence
-
Flood gates, steel frame building including pre-cast, reinforced concrete and brick work superstructure, all electrical and mechanical services
-
Extensive landscaping, drainage and services works, extensive section 278 works on adjacent dual carriageway creating suitable site access